How Long Does It Take to Build a Pool?

Real timelines, including the parts other builders leave out.

The honest answer has two parts: the part before the dig (design and permits) and the build itself. Here's how both actually run.

Before the dig: design + permits

Model/design selection can happen in a single consultation. Permitting is the wild card — it varies by city and county, typically a few weeks. We produce the plans and run the permit process for every project, so your only job is picking finishes.

The build: fiberglass

2–4 weeks for most installs. Excavation takes a day or two, the shell sets by crane in a single day (we've set two pools in one day), then leveling, plumbing, equipment, and the concrete deck. Full step-by-step on the construction process page.

The build: gunite

8–12 weeks typically: excavation, steel, plumbing rough-in, gunite shell, cure time, tile and coping, decking, plaster, fill and startup.

What actually delays pools